Pokhara-Muglin Road: Western section sees 55% physical progress
POKHARA: The physical progress of the western section (Pokhara–Jamune) of the Pokhara–Muglin road project has reached 55.10%, while financial progress stands at 42.50%, according to the project office. So far, the first layer of one-way blacktop has been completed on 37.70 km of the total 38.88 km stretch. Chief Engineer Krishna Bahadur Kunwar reported that […]